How Long Does Heat Pump Installation Take? A Day-by-Day Timeline
23 November 2026 · 6 min read
Fitting an air source heat pump usually takes 2 to 5 days on site.
Quick answer
The full process, from first survey to switch-on, normally takes 4 to 8 weeks. Most of that time is design, the grant application and booking the install.
Many homeowners worry about weeks of mess and no heating. In reality, the disruptive part is short. Your heating is usually off for one to three days. Hot water may be off for a day or two.
Here is exactly what happens, step by step.
Heat pump installation timeline at a glance
- Home survey: 1 to 3 hours — Room-by-room heat loss check, radiator and cylinder space review
- Design and quote: 1 to 2 weeks — System sizing, radiator plan, written quote
- Grant application: 1 to 3 weeks — Installer applies for the £7,500 Boiler Upgrade Scheme grant
- Network and planning checks: Days to a few weeks — Electricity network notice, permitted development check
- Installation: 2 to 5 days — Unit, cylinder, pipework, radiators and electrics fitted
- Commissioning and handover: Half a day — Testing, setup and a walk-through of controls
Step 1: The home survey (1 to 3 hours)
A proper survey is the most important step. We measure each room, check windows and insulation, and work out heat loss. This tells us what size heat pump you need.
We also check where the outdoor unit and hot water cylinder will go. And we look at your radiators and pipework. A survey that takes 20 minutes is a red flag.
Step 2: Design and quote (1 to 2 weeks)
Next, we design the system. This covers the unit size, flow temperature, radiator changes and cylinder size. You then get a clear, itemised quote.
This is a good time to ask questions. Check what is included, such as boiler removal, radiator upgrades and controls.
Step 3: Grant application (1 to 3 weeks)
Once you accept the quote, we apply for the Boiler Upgrade Scheme on your behalf. The £7,500 comes off your bill. You do not need to claim it yourself.
Ofgem usually responds within a few weeks. For air source heat pumps, the grant voucher is valid for three months, so we book your install within that window. Our guide to the £7,500 heat pump grant explains the rules in full.
Step 4: Network and planning checks
We tell your local electricity network operator about the new heat pump. Most approvals are quick. Some larger systems need extra checks, which can add a few weeks.
Most domestic heat pumps fall under permitted development, so you will not need planning permission. Listed buildings and conservation areas can differ. We check this for you at survey stage.
Step 5: Installation day by day (2 to 5 days)
Every home is different. But a typical three to four day install looks like this.
Day 1: Outdoor unit and preparation
We protect your floors and set up. The base for the outdoor unit goes in, then the unit itself. We may drain the old system and remove the gas boiler. Your heating goes off today.
Day 2: Cylinder and pipework
The new hot water cylinder is fitted. We run pipework between the outdoor unit, cylinder and heating system. Hot water is usually off for part of the day.
Day 3: Radiators
Any radiators that need upsizing are swapped. Heat pumps run at lower temperatures, so some rooms need larger radiators. Not every home needs new ones.
Day 4: Electrics and controls
Our electrician connects the unit and fits the controls. We then flush and fill the system with fresh water and inhibitor.
Smaller jobs with few radiator changes can finish in two days. Bigger homes, or homes with lots of new pipework, can take five.
Step 6: Commissioning and handover (half a day)
We switch the system on and check for leaks. Then we bleed the radiators, balance them and set the flow temperature. Finally, we show you how the controls work.
You get your MCS certificate, warranty details and paperwork. Keep these safe. You need them for the grant and for future servicing.
What can slow a heat pump installation down?
- Grant approval taking longer at busy times of year
- Extra checks from the electricity network for larger units
- Small microbore pipes that need replacing
- Lots of radiator changes in a large home
- Limited space for the hot water cylinder
- Kit availability on some brands
How to prepare for installation day
- Clear space around the boiler, cylinder area and radiators.
- Make sure there is access to the outdoor unit spot.
- Plan for a day or two without hot water.
- Have electric heaters ready if it is cold.
- Tell neighbours if there will be vans or noise.
Is winter a bad time to install a heat pump?
Not at all. We install all year round. The heating is only off for a short time, and we can leave temporary heaters if needed.
That said, spring and summer are easier if you want zero disruption. Booking early also helps you beat the autumn rush.
Book your heat pump survey
Want a clear timeline for your home? We will survey your property, plan your install and handle the grant for you. We cover Bexleyheath, Bexley and Kent.
Learn more about our air source heat pump installation, see finance options or get a free quote.
Common questions
How long does it take to install an air source heat pump?
Usually 2 to 5 days on site. The whole process takes around 4 to 8 weeks from survey to switch-on.
How long does a heat pump survey take?
Between one and three hours for most homes. Larger homes can take a little longer.
Will I be without heating during installation?
Yes, but usually only for one to three days. Hot water may be off for a day or two.
Do I need to be home during installation?
Someone should be there at the start and end of each day. You also need to be there for the handover.
How long does a heat pump take to heat a house?
Heat pumps warm homes gently and steadily. They work best left on low and steady, rather than switched on and off like a boiler.